A writing closet needs to support 20 APs and 110 wired endpoints. It has four strands of OM3 fiber to the network core 150 feet (45 m) away. The customer wants the links to the network core to support at least 10GbE. The customer also requires no loss in connectivity for the switches in the closet, even with the loss of one link.

The architect plans to recommend three 2930M 40G 8SR PoE+ switches, two 4-port SFP+ modules, and two SFP+ SR transceivers.

What should the architect change about the plan?

Show Answer
Correct Answer: B

The architect should add a stacking module for each switch and three stacking cables. This will ensure that, even with the loss of one link, the connectivity among the switches remains intact. Adding stacking modules and cables helps maintain high availability and reliability within the writing closet, which aligns with the customer's requirement of no loss in connectivity for the switches.

Discussion

2 comments
Sign in to comment
GlepersOption: B
Jul 28, 2020

I think it's B.

wifi123Option: B
Sep 16, 2020

Correct Answer is B