HPE6-A69 Exam - Question 4


What are two valid steps in a Proof of Concept plan? (Choose two.)

Show Answer
Correct Answer: AD

In a Proof of Concept plan, it is important to develop the items that need to be tested to ensure the solution’s feasibility. Additionally, evaluating the solution against success criteria is a critical step to determine how well the solution meets the objectives outlined at the beginning of the project. While the decision to move forward and validating the end-user experience are important, they are not primary steps in a Proof of Concept plan.

Discussion

1 comment
Sign in to comment
GQuirozOptions: CD
Apr 3, 2024

Aruba Advanced Switching Troubleshooting and Solutions manual, page 23