HQT-4180 Exam QuestionsBrowse all questions from this exam

HQT-4180 Exam - Question 20


You need to replace a failing power supply (PS) in a VSP E590.

What is the correct procedure?

Show Answer
Correct Answer:

Discussion

3 comments
Sign in to comment
dnet23
Jun 1, 2024

The answer in A.

jucamisternet
Jun 28, 2024

The answer is A.

Charlie76Option: B
Mar 9, 2025

The correct is B. The Maintenance Utility is used to block the failing power supply (PS) before physically replacing it​