CSM-001 Exam - Question 23


What is the maximum duration of each Sprint planning meeting section?

Show Answer
Correct Answer: C

The maximum duration of a Sprint planning meeting section is 4 hours. This is based on the guideline that for a one-month (4-week) Sprint, the total time allocated for Sprint planning is a maximum of 8 hours. Given that Sprint planning is often divided into two sections, each section would have a maximum duration of 4 hours.

Discussion

9 comments
Sign in to comment
FK411Option: C
Jan 16, 2023

Sprint planing is allowed 8 hours maximum for 4 weeks sprint. With 2 sections, 4 hours per section is the correct answer

Bakayalo
Nov 13, 2021

It should 8 hours max in 30 days sprint, no answer

Bakayalo
Nov 13, 2021

If it is require to split into 2 sections then will be 4 hours

NotImportantOption: C
Jan 24, 2022

Sprint planning is total of 8 hours. As per previous question planning is comprised of 2 sections. So each Section is 4 hours each. So as question states each section duration is 4 hours. Hence 4 is the correct answer.

ssttaarraammiittOption: C
Aug 27, 2022

1 hour max per week of sprint and max total we have 4 weeks of sprint. So ans is 4 hours.

Vin_Cho
Mar 24, 2023

might be 8h as the scrumguide is not giving any direction regarding the duration of each section

aktherajaOption: C
Apr 12, 2020

C; 4 hours max

smartsurroundingOption: D
Jan 24, 2022

I will vote for D - 2 hours. Since the max. duration of the whole Sprint Planning Meeting is 4 hours and it is split into 2 sections, 4 / 2 = 2.

AG001Option: C
Feb 2, 2023

4 is correct among these options.

Mi_WindsorOption: C
Jul 11, 2023

C is the correct action 4 hours per week