CSM-001 Exam QuestionsBrowse all questions from this exam

CSM-001 Exam - Question 41


What happens when all committed items (requirements) are not completed at the end of the Sprint?

Show Answer
Correct Answer: C

When all committed items (requirements) are not completed at the end of the Sprint, the incomplete items are returned to the product backlog. This ensures that these items can be reprioritized and considered for future sprints without extending the current Sprint's duration or discarding potentially valuable work.

Discussion

1 comment
Sign in to comment
aktherajaOption: C
Apr 12, 2020

C: returned to backlog