Question 41

What happens when all committed items (requirements) are not completed at the end of the Sprint?

    Correct Answer: C

    When all committed items (requirements) are not completed at the end of the Sprint, the incomplete items are returned to the product backlog. This ensures that these items can be reprioritized and considered for future sprints without extending the current Sprint's duration or discarding potentially valuable work.

Discussion
aktherajaOption: C

C: returned to backlog