A _____________________ is created during the first half of the Sprint planning meeting and a _________________ is created during the second half of the
Sprint planning meeting?
A _____________________ is created during the first half of the Sprint planning meeting and a _________________ is created during the second half of the
Sprint planning meeting?
During the first half of the Sprint planning meeting, the Scrum team defines the Sprint Goal, which sets the focus and objectives for the sprint. In the second half of the meeting, the team creates the Sprint Backlog, which is a detailed plan comprising the tasks and items selected from the Product Backlog that they aim to complete during the sprint.
Should be A?
A correct
Sprint backlog and respective tasks.
C is the correct answer
I thought it should be A
C, but should remove "half" term because the scrum guide is not giving any direction related to the size of those 2 parts.
C, https://guide.quickscrum.com/sprint-planning-meetings-in-scrum/