CSM-001 Exam QuestionsBrowse all questions from this exam

CSM-001 Exam - Question 9


Which of the following is not a Scrum artifact?

Show Answer
Correct Answer: A

Scrum artifacts are specific items created and maintained to provide transparency and opportunities for inspection and adaptation. The primary Scrum artifacts are the Product Backlog, Sprint Backlog, and Increment. User Stories, while commonly used in Scrum, are actually detailed descriptions of features and requirements and do not qualify as an artifact in itself.

Discussion

6 comments
Sign in to comment
RahulShaOption: A
Apr 12, 2023

User Stories are detailed explanation of features and not a scrum artifact.

AG001Option: A
Feb 2, 2023

A is correct Each artifact contains a commitment to ensure it provides information that enhances transparency and focus against which progress can be measured: ● For the Product Backlog it is the Product Goal. ● For the Sprint Backlog it is the Sprint Goal. ● For the Increment it is the Definition of Done.

san28Option: A
Mar 14, 2023

User Stories are not artifacts.

aktherajaOption: D
Feb 18, 2020

Answer is D

moon_leeOption: A
Aug 22, 2020

According to https://www.scrumalliance.org/about-scrum/artifacts , correct answer is A

patitosOption: A
Apr 3, 2022

Answer is A