CSM-001 Exam QuestionsBrowse all questions from this exam

CSM-001 Exam - Question 60


The Sprint Backlog is owned by?

Show Answer
Correct Answer: C

The Sprint Backlog is owned by the Development Team. The Development Team is responsible for managing and organizing their own work during the Sprint, including tasks listed in the Sprint Backlog. This ownership allows them to adapt to changes and take accountability for completing the necessary work items within the Sprint.

Discussion

2 comments
Sign in to comment
patitosOption: B
Apr 3, 2022

Answer is B

patitosOption: C
Apr 3, 2022

Answer is C