Question 46

On a new Scrum Team, the Development Team tell the Scrum Master that they don't feel the need for retrospectives. Which answer is correct?

    Correct Answer: B

    Retrospectives are a critical part of the Scrum framework as they allow the team to reflect on their processes and identify improvements. The Scrum Master should ensure that the team understands the importance of retrospectives and start doing them to adhere to the principles and practices of Scrum.

Discussion
Zeeshans10Option: B

if any of the scrum events is not happening, it is not scrum

FK411Option: B

B. The scrum master needs to educate the development team that all scrum events must be adhered to else it isn’t scrum.

patitosOption: B

Answer is B...The scrum master was informed so, he should encourage the team to start doing

micky123

is that mean not to have the meeting at all