CSM-001 Exam - Question 74


The _____________ Team is responsible for delivering potentially shippable product increments at the end of each Sprint.

Show Answer
Correct Answer: A

The Development Team is responsible for delivering potentially shippable product increments at the end of each Sprint. In Scrum, the Development Team is tasked with executing the work necessary to meet the Sprint goals and produce a viable product increment.