________________ constitute the Sprint Backlog and are often estimated in hours?

    Correct Answer: D

    Tasks constitute the Sprint Backlog and are often estimated in hours. During Sprint Planning, the development team breaks down User Stories or Product Backlog Items into smaller, actionable tasks and estimates the time required to complete each task. These tasks then become part of the Sprint Backlog.

Discussion
Mi_WindsorOption: D

D is the correct answer

AG001Option: D

D is correct

aktherajaOption: D

D: Tasks