Exam CSM-001 All QuestionsBrowse all questions from this exam
Question 7

The individual, detailed pieces of work that are needed to convert a product backlog item into a working software component or solution are called:

    Correct Answer: D

    The individual, detailed pieces of work that are needed to convert a product backlog item into a working software component or solution are called tasks. Tasks break down the product backlog items into smaller, manageable pieces of work for the development team to handle during a sprint or iteration.

Discussion
Mi_WindsorOption: D

D is the correct answer

AG001Option: D

D is correct

aktherajaOption: D

Answer is D