CSM-001 Exam QuestionsBrowse all questions from this exam

CSM-001 Exam - Question 73


The _____________ control model requires that every piece of work be completely understood.

Show Answer
Correct Answer: AB

The defined process control model requires that every piece of work be completely understood. This model emphasizes detailed and upfront planning to ensure that every step of the process is thoroughly comprehended and controlled.

Discussion

3 comments
Sign in to comment
SnownoodlesOption: A
Mar 15, 2020

"Empirical process control expects the unexpected, while defined process control expect every piece of work to be completely understood in upfront". The correct answer is A

mkundalOption: A
Oct 30, 2020

defined process control every piece of work is understood. In Scrum, an empirical process is implemented where progress is based on observation and experimentation instead of detailed, upfront planning and defined processes. correct ans /;A

nicesiuhungOption: A
Oct 30, 2021

why B, i think it is A