True or False: The sprint planning is a one-day time boxed meeting divided into two 4-hour sessions?
True or False: The sprint planning is a one-day time boxed meeting divided into two 4-hour sessions?
Sprint planning is a time-boxed event in Scrum, typically lasting a maximum of 8 hours for a one-month sprint. However, the duration can be shorter for shorter sprints. The description of sprint planning being divided into two 4-hour sessions is not a standardized requirement in Scrum. Therefore, the statement is false.
As per https://www.agilest.org/scrum/sprint-planning-meeting/ http://www.daily-scrum.com/scrum/sprint/planning-meeting - Answer is A
Up to sprint length....Correct answer should be B