CSM-001 Exam QuestionsBrowse all questions from this exam

CSM-001 Exam - Question 36


You are the Scrum Master. The Sprint will complete in two days. Each day of the Sprint is equivalent to 8 hours. The team has just enough time to complete all tasks in the remaining 16 hours with the exception of three tasks. Of these three tasks, two tasks (a total of 6 hours) are required to complete one Product Backlog item and one task (an estimate of 2 hours) is required to complete another Product Backlog item. How should the development team handle the remaining three tasks?

Show Answer
Correct Answer: AC

The correct approach in this situation is for the development team to place the two Product Backlog items back onto the Product Backlog. In Scrum, any work that is not completed within the Sprint should be returned to the Product Backlog for the Product Owner to re-prioritize. This ensures that the team maintains a sustainable pace and adheres to Scrum principles. Additionally, this allows the Product Owner to reassess and possibly reorder the priorities of the Product Backlog items based on the latest information and changing business needs.

Discussion

10 comments
Sign in to comment
PoojaOption: C
May 10, 2019

correct answer C

StillPatientOption: C
Jul 12, 2020

The correct answer is C

aktherajaOption: A
Apr 12, 2020

A: done definition decided by PO

meg002Option: C
Dec 29, 2022

Answer is C. Team should return any uncompleted Product Backlog Items to the Product Backlog. Business priorities may have changed, and the Product Owner may choose to re-order the Product Backlog so that this item is lower on the list than it was previously.

nicesiuhungOption: C
Oct 30, 2021

answer is C

Man4444Option: C
Dec 10, 2021

correct answer is C

AbhyagOption: A
Dec 16, 2021

Development team can't place item back to Product Log without discussing it with PO. Apt answer seems to be A

patitosOption: D
Apr 3, 2022

Answer is D..This task is already extimated meaning it should already in the sprintbacklog since No urgency applies..Then the Dev team should leave it for next sprint rather than affect the velocity of the team

mith88Option: D
Jul 20, 2022

would the answer not be D, as the team will work on the unfinished tasks in the new sprint?

RoygabibOption: A
Mar 5, 2023

A is the correct answer