CSM-001 Exam - Question 47


The correct sequence of events in using Scrum framework is as follows:

Show Answer
Correct Answer: B

The correct sequence of events in using the Scrum framework is Sprint Planning, Sprint, Daily Scrum, Sprint Review, and Sprint Retrospective. Sprint Planning occurs at the beginning of the sprint to define what will be worked on. The Sprint is the period during which the work is completed. The Daily Scrum is a short meeting held every day during the Sprint. The Sprint Review is conducted at the end of the Sprint to review the work done. Finally, the Sprint Retrospective is held to reflect on the process and discuss improvements.

Discussion

2 comments
Sign in to comment
patitosOption: C
Apr 3, 2022

Answer is C

MRabi
Apr 27, 2022

I disagree

RanitaOption: B
Nov 24, 2022

C is correct