Question 49

Who defines the Sprint Backlog scope?

    Correct Answer: B

    The Development Team defines the Sprint Backlog scope. The Sprint Backlog is an actionable plan created by the Development Team to accomplish the Sprint Goal. While the Product Owner clarifies the requirements and the Scrum Master facilitates the process, it is ultimately up to the Development Team to determine the specific tasks and estimates necessary to achieve the Sprint Goal.

Discussion
patitosOption: B

Answer is B ..While the PO clarifies if need be

brightblueOption: B

The Sprint Backlog is a plan by and for the Developers. It is a highly visible, real-time picture of the work that the Developers plan to accomplish during the Sprint in order to achieve the Sprint Goal.