The Sprint Goal is selected before the Sprint Backlog is created.
The Sprint Goal is selected before the Sprint Backlog is created.
In Scrum, the Sprint Goal is indeed selected before the Sprint Backlog is created. The Sprint Goal provides a focus for the team and helps guide the selection of Product Backlog items to be moved into the Sprint Backlog. This ensures that the team is aligned on the objective of the sprint before determining the specific tasks to accomplish it.
Answer is A