Question 25

Which of the following is not a Scrum Master responsibility?

    Correct Answer: A

    The Product Backlog is the responsibility of the Product Owner, and it is not within the Scrum Master's duties to establish priorities for it. The Scrum Master supports the team and the Product Owner and ensures adherence to Scrum practices, but setting the Product Backlog priorities is specifically a task for the Product Owner. Thus, the correct answer is the option that states the Scrum Master establishes priorities together with the Product Owner for Product Backlog items.

Discussion
JazzaOption: A

The scrum master protects the team as a Servant-Leader so they can concentrate on the task at hand, the organisation of the the Product Backlog is solely the Product owner, the scrum master is involved with the sprint backlog only, the answer here is A

SnownoodlesOption: A

One of scrum master's responsibility is to shield team from external interference, any priority change should be from PO. The right answer should be A.

Mikhil16Option: A

A should be the correct answer

AG001Option: A

A is the correct answer

hwuanghuOption: A

A is the answer

RanitaOption: A

A is correct

nicesiuhungOption: A

A is correct answer

Mi_WindsorOption: A

A is the correct answer

aktherajaOption: B

B; scrum master does not control the team