CSM-001 Exam QuestionsBrowse all questions from this exam

CSM-001 Exam - Question 39


Which of the following is NOT part of the Sprint?

Show Answer
Correct Answer: A

The product is not necessarily released to customers after each Sprint. While each Sprint aims to produce a potentially shippable product increment, releasing the product to customers typically occurs as part of a longer-term release strategy. Releases can incorporate the results of multiple Sprints based on customer and business needs.

Discussion

1 comment
Sign in to comment
brightblueOption: D
Jul 28, 2023

Scrum team determines this