Which of the following might the Scrum Team discuss during a Sprint Retrospective?
Which of the following might the Scrum Team discuss during a Sprint Retrospective?
During a Sprint Retrospective, the Scrum Team typically discusses various aspects of their process and performance to identify areas for improvement. This can include methods of communication, the way they conduct Sprint Planning, skills needed to improve the Development Team's ability to deliver, and their Definition of Done. Therefore, it is reasonable to conclude that all the provided options might be discussed during a Sprint Retrospective.
Answer is A