CSM-001 Exam QuestionsBrowse all questions from this exam

CSM-001 Exam - Question 8


Why does Scrum prevent Product Owners from changing Product Backlog items that are being worked on during the Sprint?

Show Answer
Correct Answer: A,C

Scrum prevents Product Owners from changing Product Backlog items that are being worked on during the Sprint because the development team cannot meet their Sprint commitment to complete work if requirements are changing. If the scope of the Sprint is constantly altered, it interrupts the team's focus and their ability to deliver a potentially shippable product increment by the end of the Sprint.

Discussion

7 comments
Sign in to comment
PoojaOption: A
May 10, 2019

Answer should be A

LorrenzomOption: C
Oct 16, 2019

C is the most correct ,Any changes that arises in the middle of the sprint should be added into the next sprint

AG001Option: A
Feb 2, 2023

A should be the answer

Mikhil16Option: A
Mar 10, 2023

A should be the right answer

san28Option: C
Mar 14, 2023

C is correct.

KylecyxOption: A
Jul 1, 2023

A is the correct answer

Mi_WindsorOption: A
Jul 11, 2023

A is the correct answer