Exam CSM-001 All QuestionsBrowse all questions from this exam
Question 8

Why does Scrum prevent Product Owners from changing Product Backlog items that are being worked on during the Sprint?

    Correct Answer: A

    Scrum prevents Product Owners from changing Product Backlog items that are being worked on during the Sprint because the development team cannot meet their Sprint commitment to complete work if requirements are changing. If the scope of the Sprint is constantly altered, it interrupts the team's focus and their ability to deliver a potentially shippable product increment by the end of the Sprint.

Discussion
Mi_WindsorOption: A

A is the correct answer

KylecyxOption: A

A is the correct answer

san28Option: C

C is correct.

Mikhil16Option: A

A should be the right answer

AG001Option: A

A should be the answer

LorrenzomOption: C

C is the most correct ,Any changes that arises in the middle of the sprint should be added into the next sprint

PoojaOption: A

Answer should be A