Question 26

Which of the following is reflected in a Sprint Burn down Chart?

    Correct Answer: C

    A Sprint Burndown Chart is used to track the amount of work remaining in a sprint. It helps visualize the progress of the team towards completing the sprint goal. The chart displays the number of tasks remaining, which can be used to assess whether the team is on track to complete the work by the end of the sprint. Although work hours remaining might seem relevant, the primary focus of a Sprint Burndown Chart is on tracking the remaining tasks.

Discussion
RanitaOption: C

Correct answer is C

donpet15Option: C

C is the correct answer

BakayaloOption: D

According to scrum.org Burn-down Chart: a chart which shows the amount of work which is thought to remain in a backlog. D is the answer

Bakayalo

Typo,it is C

nicesiuhungOption: C

C is the correct Answer

KamalindyaOption: C

C. "The Sprint Burndown Chart is a graph that depicts the amount of work remaining in the ongoing Sprint." SBOK 9.6.3.2

KartMagesOption: C

This Should be C. The chart shows the amount of work remaining. Chart shows Team progress towards the Sprint Goal, not in terms of time spent but in terms of how much work remains.

Mi_WindsorOption: C

That will be C

TeejobOption: B

The Scrum Burndown Chart is a visual measurement tool that shows the completed work per day against the projected rate of completion for the current project release

AbhyagOption: D

D. Sprint burndown is a graphical representation of the estimated effort-hours remaining for a given period of time during a Sprint.

nicesiuhungOption: D

should be D