CSM-001 Exam - Question 26


Which of the following is reflected in a Sprint Burn down Chart?

Show Answer
Correct Answer: CD

A Sprint Burndown Chart is used to track the amount of work remaining in a sprint. It helps visualize the progress of the team towards completing the sprint goal. The chart displays the number of tasks remaining, which can be used to assess whether the team is on track to complete the work by the end of the sprint. Although work hours remaining might seem relevant, the primary focus of a Sprint Burndown Chart is on tracking the remaining tasks.

Discussion

10 comments
Sign in to comment
KartMagesOption: C
Aug 11, 2020

This Should be C. The chart shows the amount of work remaining. Chart shows Team progress towards the Sprint Goal, not in terms of time spent but in terms of how much work remains.

KamalindyaOption: C
Dec 2, 2020

C. "The Sprint Burndown Chart is a graph that depicts the amount of work remaining in the ongoing Sprint." SBOK 9.6.3.2

nicesiuhungOption: C
Oct 30, 2021

C is the correct Answer

BakayaloOption: D
Nov 7, 2021

According to scrum.org Burn-down Chart: a chart which shows the amount of work which is thought to remain in a backlog. D is the answer

Bakayalo
Nov 7, 2021

Typo,it is C

donpet15Option: C
Nov 11, 2022

C is the correct answer

RanitaOption: C
Nov 24, 2022

Correct answer is C

nicesiuhungOption: D
Nov 1, 2021

should be D

AbhyagOption: D
Dec 16, 2021

D. Sprint burndown is a graphical representation of the estimated effort-hours remaining for a given period of time during a Sprint.

TeejobOption: B
Jan 31, 2023

The Scrum Burndown Chart is a visual measurement tool that shows the completed work per day against the projected rate of completion for the current project release

Mi_WindsorOption: C
Jun 21, 2023

That will be C