CSM-001 Exam - Question 12


_____________ can change the priority of items in the _________ backlog at any time.

Show Answer
Correct Answer: C

The Product Owner(s) can change the priority of items in the Product backlog at any time because they are responsible for ensuring that the backlog is prioritized appropriately to maximize the value of the team's work. The Product backlog is a dynamic list that reflects the evolving needs and priorities of the product being developed, and the Product Owner(s) have the authority to make changes to it as required.