Question 21

During a Sprint Planning, a team has picked three User Stories:

✑ Story 1 "" 5 Story Points

✑ Story 2 "" 8 Story Points

✑ Story 3 "" 3 Story Points

At the end of the Sprint, the team has completed Story 1 and Story 3 and the Product Owner accepts these. The team has almost completed Story 2 but there are a few bugs identified in acceptance tests.

What is the Velocity of this team?

    Correct Answer: A

    Velocity is calculated based on the number of story points that are fully completed and accepted by the Product Owner during a sprint. Unfinished work, even if it is close to completion, does not count towards the velocity. In this case, the team completed Story 1 (5 points) and Story 3 (3 points) which makes a total of 8 points. Hence, the velocity of the team is 8 points.

Discussion
juzerOption: A

8 points

foxpro7Option: D

The Correct answer is D. Insufficient information given it depends on % completion of Story 2.

vdc47

HI Anny_Me were you able to pass the examination using these dumps ?

Anny_MeOption: B

In Exin's recent document, it is shown "unfinished work cannnot be counted or taken into consideration when measuring the velocity" in page 130. So I think B is correct

Nosrat

again, if the shown answer is wrong, please correct it. This kind of uncertainty on answers can only confuse and endanger the certification tests for us.