ASM Exam - Question 21


During a Sprint Planning, a team has picked three User Stories:

✑ Story 1 "" 5 Story Points

✑ Story 2 "" 8 Story Points

✑ Story 3 "" 3 Story Points

At the end of the Sprint, the team has completed Story 1 and Story 3 and the Product Owner accepts these. The team has almost completed Story 2 but there are a few bugs identified in acceptance tests.

What is the Velocity of this team?

Show Answer
Correct Answer: A

Velocity is calculated based on the number of story points that are fully completed and accepted by the Product Owner during a sprint. Unfinished work, even if it is close to completion, does not count towards the velocity. In this case, the team completed Story 1 (5 points) and Story 3 (3 points) which makes a total of 8 points. Hence, the velocity of the team is 8 points.

Discussion

5 comments
Sign in to comment
juzerOption: A
Apr 26, 2020

8 points

foxpro7Option: D
Aug 5, 2021

The Correct answer is D. Insufficient information given it depends on % completion of Story 2.

Nosrat
May 23, 2022

again, if the shown answer is wrong, please correct it. This kind of uncertainty on answers can only confuse and endanger the certification tests for us.

Anny_MeOption: B
Aug 12, 2022

In Exin's recent document, it is shown "unfinished work cannnot be counted or taken into consideration when measuring the velocity" in page 130. So I think B is correct

vdc47
Sep 20, 2022

HI Anny_Me were you able to pass the examination using these dumps ?