Question 1

Your team uses Story Points to estimate User stories.

Halfway through a Sprint, you are not seeing the progress you expected. The Team feels some Stories are not estimated correctly, when compared to other

Stories.

How should you address this?

    Correct Answer: C

    When stories are not estimated correctly, it's important to revisit the estimates to ensure they accurately reflect the effort required. Re-estimating all small stories can help recalibrate the team's understanding of story points and ensure consistency in future estimates. This approach helps address discrepancies without disrupting the team's process by changing the estimation method or focusing only on completing unfinished stories.