ASM Exam QuestionsBrowse all questions from this exam

ASM Exam - Question 32


After the creation of the Release Plan, the Product Owner says:

The Scrum Master argues that the end date of the release can be positively or negatively impacted by three factors. Completed work is the first factor.

What are the other two factors?

Show Answer
Correct Answer: B

The end date of the release can be impacted by changed requirements and revised estimates. Changed requirements can lead to additional work or alterations in the development process, and revised estimates can reflect new information or insights about the scope, complexity, or effort needed for the work, which in turn affects the schedule.

Discussion

1 comment
Sign in to comment
clsmooth
Oct 29, 2022

What the PO says is missing...