Question 32

After the creation of the Release Plan, the Product Owner says:

The Scrum Master argues that the end date of the release can be positively or negatively impacted by three factors. Completed work is the first factor.

What are the other two factors?

    Correct Answer: B

    The end date of the release can be impacted by changed requirements and revised estimates. Changed requirements can lead to additional work or alterations in the development process, and revised estimates can reflect new information or insights about the scope, complexity, or effort needed for the work, which in turn affects the schedule.

Discussion
clsmooth

What the PO says is missing...