Question 27

A Development Team consists of various different roles: analysts, programmers, UX experts, DBA and systems architects. They are estimating Backlog Items in

Ideal Days.

What is the best approach to provide estimates for the Backlog Items?

    Correct Answer: C

    In Scrum, the responsibility for estimating the effort required for backlog items lies with the Development Team collectively. This ensures that all perspectives and expertise within the team are considered and integrated into a single estimate. This approach promotes collaboration and shared understanding, leading to more accurate and realistic estimates. Estimating in 'Ideal Days' is a common practice, and if it is being used, the Development Team should provide a single estimate for each backlog item rather than separate estimates that need to be integrated by another party.

Discussion
foxpro7Option: B

B is the answer . Ideal days' estimation is not feasible in this case; Story Points should be used

kschinchinOption: B

shd be B