A Development Team consists of various different roles: analysts, programmers, UX experts, DBA and systems architects. They are estimating Backlog Items in
Ideal Days.
What is the best approach to provide estimates for the Backlog Items?
A Development Team consists of various different roles: analysts, programmers, UX experts, DBA and systems architects. They are estimating Backlog Items in
Ideal Days.
What is the best approach to provide estimates for the Backlog Items?
In Scrum, the responsibility for estimating the effort required for backlog items lies with the Development Team collectively. This ensures that all perspectives and expertise within the team are considered and integrated into a single estimate. This approach promotes collaboration and shared understanding, leading to more accurate and realistic estimates. Estimating in 'Ideal Days' is a common practice, and if it is being used, the Development Team should provide a single estimate for each backlog item rather than separate estimates that need to be integrated by another party.
B is the answer . Ideal days' estimation is not feasible in this case; Story Points should be used
shd be B