Why is a Product Owner not allowed to define the workload of the Development Team for a new Sprint?
Why is a Product Owner not allowed to define the workload of the Development Team for a new Sprint?
A Product Owner is not allowed to define the workload of the Development Team because this conflicts with the principle of Self-Management. In Scrum, one of the core principles is that the Development Team is self-managing, meaning they have the autonomy to decide how much work they can commit to during a Sprint. This ensures that the team retains control over their work process and can maintain a sustainable pace.
This conflicts with the principle of Self-Management of the Development Team.
Le PO ne se charge pas de process
The conflict with the principle of self organize team
The conflict with the principle of self organize team