Why is a Product Owner not allowed to define the workload of the Development Team for a new Sprint?
Why is a Product Owner not allowed to define the workload of the Development Team for a new Sprint?
A Product Owner is not allowed to define the workload of the Development Team because this conflicts with the principle of Self-Management. In Scrum, one of the core principles is that the Development Team is self-managing, meaning they have the autonomy to decide how much work they can commit to during a Sprint. This ensures that the team retains control over their work process and can maintain a sustainable pace.
This conflicts with the principle of Self-Management of the Development Team.
The conflict with the principle of self organize team
Le PO ne se charge pas de process