DES-1423 Exam QuestionsBrowse all questions from this exam

DES-1423 Exam - Question 7


A company’s Isilon cluster has reached the capacity limit. The cluster consists of eight H500 nodes in a single node pool. Which action can be taken to resolve the capacity issue while new nodes are being delivered?

Show Answer
Correct Answer: C

To resolve capacity issues temporarily while new nodes are being delivered, enabling Spillover would be the most appropriate action. Spillover allows a cluster to continue to function by spilling over the data to other nodes or tiers temporarily, thus mitigating the immediate capacity constraints. Other options like activating SmartPools or GNA may not directly address the immediate capacity issue.

Discussion

4 comments
Sign in to comment
Kakorat
Oct 27, 2023

D is correct

pacovillalbaoutlook
May 30, 2023

Answer is D VHS is available with the licensed and unlicensed SmartPools module. By default, all available free space on a cluster is used to rebuild data. The virtual hot spare option reserves free space for this purpose.

Xperience
Jul 24, 2023

D is the correct answer

Whitesnake592Option: D
Dec 3, 2024

D is correct