Which key metric should be used when updating the corporate disaster recovery plan to minimize data loss?

    Correct Answer: C

    The key metric that should be used when updating the corporate disaster recovery plan to minimize data loss is the Recovery Point Objective (RPO). RPO defines the maximum acceptable amount of data loss measured in time before a disaster occurs. By aiming for a lower RPO, organizations can ensure that they would lose less data in the event of a disaster.

Discussion
patrickengOption: C

Correct answer C. The lower the RPO (Recovery Point Object), the less data loss in case of disasters.

CSheikOption: C

C - The question is about Disaster Recovery

loganvmOption: D

Should be RTO