Which is the correct order of installation for PAS components?
Which is the correct order of installation for PAS components?
The correct order of installation for PAS components starts with PVWA, then Vault, followed by CPM, and finally PSM. This sequence ensures that the foundational components are in place before the dependent components are installed.
All options are wrong. It would be Vault->PVWA->CPM->PSM.
You are right.
The actual order is Vault > PVWA > CPM > PSM > PTA . Reference link: https://docs.cyberark.com/Product-Doc/OnlineHelp/PAS/11.3/en/Content/PAS%20INST/InstallationOverview.htm