Question 46

Which is the correct order of installation for PAS components?

    Correct Answer: D

    The correct order of installation for PAS components starts with PVWA, then Vault, followed by CPM, and finally PSM. This sequence ensures that the foundational components are in place before the dependent components are installed.

Discussion
Kaustav01

All options are wrong. It would be Vault->PVWA->CPM->PSM.

NLT

You are right.

NLT

The actual order is Vault > PVWA > CPM > PSM > PTA . Reference link: https://docs.cyberark.com/Product-Doc/OnlineHelp/PAS/11.3/en/Content/PAS%20INST/InstallationOverview.htm