CAU302 Exam QuestionsBrowse all questions from this exam

CAU302 Exam - Question 46


Which is the correct order of installation for PAS components?

Show Answer
Correct Answer: D

The correct order of installation for PAS components starts with PVWA, then Vault, followed by CPM, and finally PSM. This sequence ensures that the foundational components are in place before the dependent components are installed.

Discussion

2 comments
Sign in to comment
Kaustav01
Jun 22, 2022

All options are wrong. It would be Vault->PVWA->CPM->PSM.

NLT
Dec 16, 2022

You are right.

NLT
Dec 16, 2022

The actual order is Vault > PVWA > CPM > PSM > PTA . Reference link: https://docs.cyberark.com/Product-Doc/OnlineHelp/PAS/11.3/en/Content/PAS%20INST/InstallationOverview.htm