Question 161

A PM is working on the schedule for a project that has technical tasks and requires a SME's knowledge. The PM decides the best way to track this project is to have the project lead provide high-level updates. Which of the following is the BEST tool to track this data?

    Correct Answer: D

    A Milestone chart is the best tool for tracking high-level updates on a project. It focuses on key deliverables and milestones which are ideal for summarizing the progress of the project without delving into the detailed tasks, making it easier for the project lead to provide clear and concise updates.

Discussion
eXhilarat3dOption: D

From AI source... A Milestone chart is a management tool that is used to depict project milestones and their dates of completion in a simplified, high-level manner.