Several stakeholders have declined the invitation for the kickoff of a major digital transformation project. Which of the following actions should the project manager take NEXT?
Several stakeholders have declined the invitation for the kickoff of a major digital transformation project. Which of the following actions should the project manager take NEXT?
Proceeding with the kickoff meeting as planned is the best approach to maintain the project's schedule and momentum. Delaying the meeting or escalating the issue immediately might cause unnecessary delays and disruptions. The project manager can later arrange separate sessions or follow-up meetings with the stakeholders who could not attend the kickoff to ensure they are informed and aligned with the project's objectives and plan.
Per AI source... C. Proceed with the kickoff as planned: It is important to maintain the project schedule and proceed with the kickoff meeting as planned to avoid delays. The project manager can then schedule separate sessions with the stakeholders who were unable to attend to cover the key points and ensure they are aligned with the project’s objectives and plan.