Which of the following activities would be performed during the project closure phase when the waterfall methodology is being used? (Choose two.)
Which of the following activities would be performed during the project closure phase when the waterfall methodology is being used? (Choose two.)
During the project closure phase in the waterfall methodology, validating the deliverables and reconciling the project budget are key activities. Validating the deliverables ensures that all the project outputs meet the specified requirements and function as intended before formally closing the project. Reconciling the project budget involves reviewing and comparing the actual project expenditures against the initial budget to identify any cost variances and gather insights for future budgeting processes.
Per AI source... E. Validating the deliverables and F. Reconciling the project budget. Here's why these options are the most suitable for project closure in Waterfall: E. Validating Deliverables: Waterfall follows a sequential delivery approach. In closure, it's crucial to formally verify and validate all project deliverables ensure they meet requirements and function as intended. F. Reconciling the Project Budget: Project closure involves comparing actual expenditures against the planned budget. This reconciliation helps identify any cost variances and provides valuable insights for future project cost estimation.