During an agile project, a team member checked the project artifacts in order to anticipate when all the work should have been completed. Which of the following charts was the team member MOST likely consulting?
During an agile project, a team member checked the project artifacts in order to anticipate when all the work should have been completed. Which of the following charts was the team member MOST likely consulting?
A burndown chart is commonly used in agile methodologies to track the progress of work over time. It shows the amount of work remaining versus time, allowing team members to anticipate when all work will be completed. By regularly checking the burndown chart, team members can gauge whether they are on track to complete their tasks within the remaining timeframe of the sprint or project.
Burndown chart: This is a staple of Agile methodologies. It visually tracks the remaining work in a sprint by plotting the amount of work left (user stories, tasks, etc.) against time. By looking at the trend of the burndown chart, a team member can get a sense of when the remaining work is likely to be completed.