Exam 300-410 All QuestionsBrowse all questions from this exam
Question 243

Refer to the exhibit. R6 should reach R1 via R5>R2>R1. Which action resolves the issue?

    Correct Answer: C

    To ensure R6 reaches R1 via R5 > R2 > R1, we need to make the current least-cost path (R5 > R2 > R3 > R1) less favorable. By increasing the cost between R2 and R3 to 61, the total cost of the path through R3 becomes higher (20+61=81), making the path via R5 > R2 > R1 (20+20=40) the preferred route. Therefore, the correct action is to increase the cost between R2 and R3 to 61.

Discussion
HungarianDishOption: C

Agree with Demir11's calculation.

pepguaOption: C

Increase cost BY 61. Keyword BY, not TO 61. When you increase BY 61, total becomes 81 which is what you want to achieve.

bucket12678

I detest how these are worded sometimes. Technically speaking, if you increase the cost TO 61, then the cost of the link = 61 (in which case, it doesn't use the R1-R2 link). However, if you increase the cost BY 61, then the cost of the link = 81 (20+61). This is just splitting hairs over semantics, but the question is worded incorrectly.

[Removed]Option: B

Basically due to the lowest cost the path it is taking before the change is R6-R5-R2-R3-R1 Increasing the cost by 61 makes the total cost 81>80 so it will prefer R1

SeMo0o0o0Option: C

C is corerct

6dd4aa0Option: D

See the answer provided by sol_ls95. I agreed with the user.

pulsetion

What sol_ls95 said is incorrect. This would make 6-5-2-1= 81 and 6-5-2-3-1=80.

sol_ls95Option: A

a)6-5-2-1=82 6-5-2-3-1=42 b)6-5-2-1=120 6-5-2-3-1=111 c)6-5-2-1=120 6-5-2-3-1=141 d)6-5-2-1=81 6-5-2-3-1=89

pyrokar

The calculation for d is wrong or probably a typo, 6-5-2-3-1=80. Thus the solution is C.

babs

can someone explain this?

ellen_AA

On each suggestion, try replace the cost with the suggested one, then sum from R6 all the way to R1. You'll find that answer C presents the lowest cost possible to choose the path R5>R2>R1