Exam 156-3158120 All QuestionsBrowse all questions from this exam
Question 49

What order should be used when upgrading a Management High Availability Cluster?

    Correct Answer: D

    In a Management High Availability Cluster, it is essential to first upgrade the Primary Management server before upgrading the Secondary Management server. This ensures that the primary server can maintain its management capabilities and continue to perform critical functions while the secondary server is being upgraded.

Discussion
KuKuKu83Option: D

"In Management High Availability, make sure the Primary Security Management Server is upgraded and runs, before you start the upgrade on other servers."

RajeshkashiOption: D

Answer is D