Question 12

How many versions, besides the destination version, are supported in a Multi-Version Cluster Upgrade?

    Correct Answer: D

    In a Multi-Version Cluster Upgrade, one version besides the destination version is supported. This means that during the upgrade process, you can have one additional version that the cluster can support along with the final destination version.

Discussion
KuKuKu83Option: D

correct 1 "Version X" is allowed to be only one of these: R77.30, R80.10, R80.20, and so on. https://sc1.checkpoint.com/documents/R81/WebAdminGuides/EN/CP_R81_Installation_and_Upgrade_Guide/Topics-IUG/MVC-Upgrade-Supported-Versions.htm so due to "besides the destination version" 1 other version is correct