Exam APD01 All QuestionsBrowse all questions from this exam
Question 42

Which of the following statements about the status of a work queue is/are correct?

1. The status can be used as a method of recording what work has been done so far on a Work Queue item

2. The status is set using the Update Status action of the Work Queues business object

3. Every time the Update Status action is executed, the existing status is appended. Each status is separated with a semi colon.

4. The status can be used to aid manual working of exceptions; providing the Item Status can inform staff what work is still outstanding on an item that needs manually completing

    Correct Answer: B

    The status of a work queue can be used to record what work has been done so far on a Work Queue item, it can be set using the Update Status action of the Work Queues business object, and it can aid in the manual working of exceptions by informing staff about the work still outstanding on an item. However, the statement that the status is appended every time the Update Status action is executed is incorrect. Therefore, options 1, 2, and 4 are correct.

Discussion
LH1213Option: B

I think B is the correct answer

KarolAndrzejOption: B

B. Status cannot be appended, it is replaced hence 1,2,4

AscarOption: B

B? 1,2,4