Exam RCDD-001 All QuestionsBrowse all questions from this exam
Question 74

Which area of project management covers the blending of various subteams into a project organization with a cohesive plan?

    Correct Answer: A

    The area of project management that covers the blending of various subteams into a project organization with a cohesive plan is Integration Management. This involves ensuring that all aspects of the project are properly coordinated and executed in a unified manner.

Discussion
CUB90

TDMM page 21-6 (1537) Telecommunication Project Management (TPM) Knowledge Areas.