Exam RCDD-001 All QuestionsBrowse all questions from this exam
Question 70

At the end of the second week of a project, the earned value (EV) of work is $8000 USd and the planned value (PV) of work is $7000 USd. What is true about the project?

    Correct Answer: A

    In project management, if the earned value (EV) is greater than the planned value (PV), it indicates that the project is ahead of schedule. In this case, the EV is $8000 while the PV is $7000, meaning the project has accomplished more work than was planned for this point in time.

Discussion
CUB90

TDMM page 21-24 (1555)