RCDD-001 Exam QuestionsBrowse all questions from this exam

RCDD-001 Exam - Question 70


At the end of the second week of a project, the earned value (EV) of work is $8000 USd and the planned value (PV) of work is $7000 USd. What is true about the project?

Show Answer
Correct Answer: A

In project management, if the earned value (EV) is greater than the planned value (PV), it indicates that the project is ahead of schedule. In this case, the EV is $8000 while the PV is $7000, meaning the project has accomplished more work than was planned for this point in time.

Discussion

1 comment
Sign in to comment
CUB90
Nov 19, 2023

TDMM page 21-24 (1555)