Question 99

Exhibit:

In this future marina layout, assuming that there are fewer than 10 slips being cabled, what would be the pre-cabling guideline to follow for terminal A?

    Correct Answer: A

    The pre-cabling guideline to follow for terminal A in this future marina layout involves installing one or two pair cables from the boat slips to a distribution terminal on the closest point of land. This ensures a straightforward and cost-effective installation, appropriate for a setup with fewer than 10 slips being cabled. The other options involve more extensive and possibly unnecessary measures for such a small number of slips.

Discussion
CUB90

What is the difference between questions #4 and #6 on this topic? Similar questions with different answers. Can someone explain?