Question 9

Tom needs to work on scheduling and reordering future Sprints in a project.

What are the minimum two permissions that Tom needs? (Choose two.)

    Correct Answer: E, F

    To work on scheduling and reordering future Sprints, Tom needs 'Schedule Issues' to manage the timing and ordering of tasks within the sprints, and 'Manage Sprints' to create, edit, and reorder the sprints themselves. These permissions are essential for handling sprints effectively.

Discussion
Christian_gutanOptions: DF

D&F are the correct ones