Exam ACP-600 All QuestionsBrowse all questions from this exam
Question 35

A project has a single issue type named Task to manage Bugs and Feature Requests.

What requirement would result in the need to create an additional issue type to manage Bugs?

    Correct Answer: C

    Creating an additional issue type to manage Bugs would be necessary if different fields are needed when creating, editing, or viewing Tasks compared to Bugs. This requirement signifies that there is a need for a clear distinction in the type of information captured and displayed for Bugs versus other Tasks, thus necessitating a separate issue type for Bugs.

Discussion
rmahankali

C and D