Question 52

Scrum Masters must be able to manage sprints in a particular project, but they are unable to do so.

You need to recommend an action to the Jira administrator which satisfies their requirement.

Which recommendation will definitely NOT satisfy their requirement?

    Correct Answer: A

    Adding Application access (Jira Core) to the Manage Sprints permission will definitely NOT satisfy the requirement. Scrum Masters need specific project permissions to manage sprints. Simply adding application access does not grant the necessary project-level permissions. Instead, permissions must be managed at the project level, such as adding the Scrum-Masters project role or group to the Manage Sprints permission.

Discussion
tonycamachoOption: A

Correct Answer is A

rmahankaliOption: C

I think its C because even if you add a user as SM; he/she will still NOT be able to perform the operation