An issue is showing the Time Tracking section as follows:

There is clearly an hour's difference between the Original and Remaining estimates.

Identify two possible reasons Logged Time is showing as Not Specified. (Choose two.)

Show Answer
Correct Answer: ABF

There are two possible reasons why Logged Time is showing as Not Specified. First, if time tracking was not enabled during the time the work was logged, it would not register correctly, leading to the logged time appearing as Not Specified. Second, if you do not have the necessary view permissions to see the logged work, it will also appear as Not Specified to you, even though it might be logged in the system. The other options do not directly account for why the logged time would show as Not Specified while there is a disparity between Estimated Time and Remaining Time.

Discussion

2 comments
Sign in to comment
cloudstudy12358Options: BE
Aug 30, 2021

The answers I chose were B, E

DdaGOptions: AB
May 11, 2022

I think it is A, B