Question 51

Your Scrum Software type project only uses a single shared workflow.

The resolution needs to be set manually during the Fix transition.

As a project administrator, how can you achieve this?

    Correct Answer: D

    To set the resolution manually during the Fix transition in a Scrum Software project that uses a single shared workflow, you need to request a screen with the Resolution field to be associated with the Fix transition. This ensures that users can set the resolution directly when executing the Fix transition.

Discussion
LordiTHOption: D

E is wrong it must be D.

rmahankaliOption: D

It is D