CQE Exam - Question 38


The example of a supplier's quality management effort to meet your existing contractual requirements is MOST like

I. A product audit.

II. A process audit.

III. A system audit.

Show Answer
Correct Answer: B,D

A supplier's quality management effort to meet your existing contractual requirements is broadly reflective of their overall approach to quality, which is assessed through various kinds of audits. A product audit ensures that the final product meets the specified requirements, a process audit examines the processes to ensure they are capable and effective, and a system audit evaluates the supplier's total quality management system. Thus, it is accurate to say that it involves a product audit, a process audit, and a system audit.

Discussion

2 comments
Sign in to comment
adance1Option: B
Aug 21, 2020

A system audit

Sachindra_89Option: B
Jan 14, 2023

Process audit is mandatory