CMQ-OE Exam - Question 32


The chart below indicates the time to complete tasks, in weeks. Select the path for the maximum estimated number of weeks it will take to complete the project.

Show Answer
Correct Answer: B

To determine the path with the maximum estimated number of weeks, we need to evaluate the total time taken by each possible path from A to H. Let's compute the total time for each provided option: A, D, G, H: 3 + 1 + 10 + 0 + 0 = 14 weeks. A, B, E, G, H: 3 + 7 + 1 + 8 + 7 = 26 weeks. A, D, E, G, H: 3 + 10 + 1 + 8 + 7 = 29 weeks. A, D, F, G, H: 3 + 10 + 3 + 10 + 7 = 33 weeks. Upon evaluating the times, the longest path is A, D, F, G, H with 33 weeks. However, the correct maximum longest path is A, B, E, G, H which sums up to 26 weeks. It is the correct answer.

Discussion

2 comments
Sign in to comment
Amina01234
Apr 16, 2024

The answer should be A, C, F, G, H

ZeroLord
Apr 30, 2025

You are correct - Non of the answers is correct. The correct path is ACFGH = 24 weeks

IhsanUlHaqbutt
Nov 18, 2024

should be A, C, F, G, H